Discharge of planning conditions
Contents |
[edit] Introduction
Rather than refusing a planning application, a planning authority might grant permission, but with attached planning conditions. Some conditions may require approval by the planning authority before development commences (such as agreeing the colour of materials), others can be discharged during the course of development (for example limits to site operating hours).
Conditions imposed on a planning permissions are set out in the decision notice. The nature of conditions varies depending on the nature of the development and should be tailored to deal with specific issues rather than standardised or used to impose unnecessary controls. The National Planning Policy Framework states that planning conditions should only be imposed where they are ‘necessary, 'relevant to planning and to the development to be permitted, enforceable, precise and reasonable in all other respects’.
[edit] Methods for discharging a condition
The exact method for applying to discharge a planning condition depends on the local planning authority and therefore consultation with them is advisable. Typically, their website may include a discharge of conditions application form that can be downloaded and submitted or they may advise that application should be made through the planning portal website.
If early consultation takes place with the local planning authority before the application is submitted, or before the planning committee meeting, it may be possible to broadly agree the nature of conditions that the planning committee are likely to impose and the method of discharge.
[edit] Fees
It is necessary for an applicant to pay a fee to the local planning authority when they apply for:
- Written confirmation that conditions have been discharged.
- Written confirmation that one or more of the conditions has been completed.
More information on fees is available from the Planning Practice Guidance website. Typically, a fee of £116 (or £34 for householder planning permission) is payable per submission in England, to discharge the requirements of a planning condition.
[edit] Duration
For straightforward cases a response to an application to discharge planning conditions should be given within 21 days. This includes situations in which the condition requires third party consultation for discharge. Planning authorities must provide notice of their decision within 8 weeks from the date the request was submitted. If after 12 weeks, no decision has been received (and even if an extension of time is agreed for discharging the condition), the fee must be returned to the applicant.
[edit] Failure to comply
All conditions attached to a planning decision must be complied with, and failure to do so could lead to planning enforcement action being undertaken against the applicant or could lead to the invalidation of the planning permission.
Local planning authorities may undertake inspections to check planning conditions have been discharged and to ensure that development is in compliance with the permission that has been granted.
[edit] Deemed discharge
In April 2015, the deemed discharge of planning conditions was introduced into the Town and County Planning Act 1990 by the Infrastructure Act 2015. Details of the provisions are set out in the Town and Country Planning (Development Management Procedure) Order 2015.
This allows certain types of planning conditions in England to be discharged upon application if a local planning authority has not notified the developer of their decision within the prescribed time period. This is intended to improve the use of planning conditions and enable development to start more quickly after planning permission is granted.
See Deemed discharge of planning conditions for more information.
[edit] Find out more
Related articles on Designing Buildings Wiki.
- Consultation process.
- Deemed discharge of planning conditions.
- Detailed planning application.
- Outline planning application.
- National Planning Policy Framework.
- Planning permission.
- Planning appeal.
- Planning enforcement.
- Planning fees.
- Planning objection.
- Planning obligation.
- Viability test.
External references
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.